Training Name | Training Provider | Duration | Date Completed | Verified by RSA Panel | |
Continued Professional Development – Road Safety Audit Practice | Main Roads WA / IPWEA | 2 days | 20/11/2023 | ✔ | |
Safe System for Road Engineers and Managers | University of Adelaide | 1 day | 22/10/2022 | ✔ | |
Roadworks Traffic Manager | Main Roads WA | Other | 24/09/2020 | ✔ | |
Road Safety Engineering - Treatment of Crash Locations | IPWEA | 2 days | 08/08/2019 | ✔ | |
Road Safety Audit | IPWEA | 3 days | 04/04/2019 | ✔ | |
Advanced Worksite Traffic Management | AusQ Training | 4 days | 29/06/2018 | ✔ |
Date of Audit | Location Type | Stage of Audit | Project Type | Details |
Current 5 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | - | - | - |
Cycling Facilities | - | - | - | - | - |
Grade Separation | - | - | - | - | - |
Intersection Improvements Major | - | - | - | - | - |
Intersection Improvements Minor | - | - | - | - | - |
Land Use Development | - | - | - | - | - |
Local Traffic Management Project | - | - | - | - | - |
New Road Project | - | - | - | - | - |
New roundabout | - | - | - | - | - |
Pedestrian Facilities | - | - | - | - | - |
Public Transport Project Major | - | - | - | - | - |
Public Transport Project Minor | - | - | - | - | - |
Road Safety Inspection – Intersection | - | - | - | - | - |
Road Safety Inspection – Route | - | - | - | - | - |
Rural Road Upgrade | - | - | - | - | - |
Rural Route Treatment | - | - | - | - | - |
Safety Barrier Project | - | - | - | - | - |
Shared use Facilities | - | - | - | - | - |
Signalised Intersection | - | - | - | - | - |
Streetscape Works | - | - | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | - | - |
Urban Road Upgrade | - | - | - | - | - |
Urban Route Treatment | - | - | - | - | - |
Totals | 0 | 0 | 0 | 0 | 0 |
Current 10 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | - | - | - |
Cycling Facilities | - | - | - | - | - |
Grade Separation | - | - | - | - | - |
Intersection Improvements Major | - | - | - | - | - |
Intersection Improvements Minor | - | - | - | - | - |
Land Use Development | - | - | - | - | - |
Local Traffic Management Project | - | - | - | - | - |
New Road Project | - | - | - | - | - |
New roundabout | - | - | - | - | - |
Pedestrian Facilities | - | - | - | - | - |
Public Transport Project Major | - | - | - | - | - |
Public Transport Project Minor | - | - | - | - | - |
Road Safety Inspection – Intersection | - | - | - | - | - |
Road Safety Inspection – Route | - | - | - | - | - |
Rural Road Upgrade | - | - | - | - | - |
Rural Route Treatment | - | - | - | - | - |
Safety Barrier Project | - | - | - | - | - |
Shared use Facilities | - | - | - | - | - |
Signalised Intersection | - | - | - | - | - |
Streetscape Works | - | - | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | - | - |
Urban Road Upgrade | - | - | - | - | - |
Urban Route Treatment | - | - | - | - | - |
Totals | 0 | 0 | 0 | 0 | 0 |
Current 5 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | 5 | 2 | 1 |
Cycling Facilities | - | - | - | - | - |
Grade Separation | - | - | - | - | - |
Intersection Improvements Major | - | - | - | 3 | - |
Intersection Improvements Minor | - | - | - | - | 1 |
Land Use Development | - | 2 | 1 | - | - |
Local Traffic Management Project | - | - | - | - | 1 |
New Road Project | - | - | - | 1 | - |
New roundabout | 1 | - | 1 | 2 | - |
Pedestrian Facilities | - | - | - | - | - |
Public Transport Project Major | - | - | - | - | - |
Public Transport Project Minor | - | - | - | - | - |
Road Safety Inspection – Intersection | - | - | - | - | 3 |
Road Safety Inspection – Route | - | - | - | - | 2 |
Rural Road Upgrade | 3 | - | - | 3 | - |
Rural Route Treatment | - | - | - | - | - |
Safety Barrier Project | - | - | - | - | - |
Shared use Facilities | - | - | - | - | - |
Signalised Intersection | - | - | - | - | - |
Streetscape Works | - | - | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | - | - |
Urban Road Upgrade | - | - | - | - | - |
Urban Route Treatment | - | - | - | - | - |
Totals | 4 | 2 | 7 | 11 | 8 |
Current 10 Years | |||||
---|---|---|---|---|---|
Project Type | Feasibility | Preliminary Design | Detailed Design | Pre/Post opening | Road Safety Inspection |
Blackspot project | - | - | 5 | 2 | 1 |
Cycling Facilities | - | 1 | - | - | - |
Grade Separation | - | - | - | - | - |
Intersection Improvements Major | - | - | - | 3 | - |
Intersection Improvements Minor | - | - | 1 | - | 1 |
Land Use Development | - | 2 | 1 | - | - |
Local Traffic Management Project | - | - | - | - | 1 |
New Road Project | - | 1 | - | 1 | - |
New roundabout | 1 | - | 1 | 2 | - |
Pedestrian Facilities | - | - | - | - | - |
Public Transport Project Major | - | - | - | - | - |
Public Transport Project Minor | - | - | - | - | - |
Road Safety Inspection – Intersection | - | - | - | - | 5 |
Road Safety Inspection – Route | - | - | - | - | 2 |
Rural Road Upgrade | 3 | - | - | 3 | - |
Rural Route Treatment | - | - | - | - | - |
Safety Barrier Project | - | - | - | - | - |
Shared use Facilities | 1 | - | - | 1 | - |
Signalised Intersection | - | - | - | - | - |
Streetscape Works | - | 1 | - | - | - |
Traffic Calming | - | - | - | - | - |
Unsignalised Intersection | - | - | - | - | - |
Urban Road Upgrade | - | - | - | - | - |
Urban Route Treatment | - | - | - | - | - |
Totals | 5 | 5 | 8 | 12 | 10 |